Bennett Park
Bennett Park Abatement & Demolition Project Schedule
Updated 8/3/2022
Music & Design Building
-
Fully abated
-
Demo / Wrecking complete
-
Foundation infill complete
-
Rough grading complete
Science Building
-
Fully abated
-
Demo / Wrecking complete
-
Foundation infill complete
-
Rough grading complete
Dance Building
-
Fully abated
-
Demo / Wrecking complete
-
Foundation infill complete
-
Rough grading complete
Hale House
-
Fully abated
-
Demo / Wrecking on-hold
-
Foundation infill complete
-
Rough grading complete
Carroll Hall
-
Fully abated
-
Demo / Wrecking on-hold
-
Foundation infill complete
-
Rough grading complete
Alumnae Hall
-
Fully abated
-
Demo / Wrecking on-hold
-
Foundation infill complete
-
Rough grading complete
Boiler House
-
Fully abated
-
Demo / Wrecking on-hold
-
Foundation infill complete
-
Rough grading complete
Chapel
-
Fully abated
-
Demo / Wrecking on-hold
-
Foundation infill complete
-
Rough grading complete
Library
-
Fully abated
-
Demo / Wrecking on-hold
-
Foundation infill complete
-
Rough grading complete
Tudor Mansion Complex (Halcyon Hall)
-
Fully abated
-
Demo / Wrecking on-hold
-
Foundation infill complete
-
Rough grading complete
Final Grading / Soil & Seeding
-
The site work is anticipated to be complete in 2022
Note: The landscape redevelopment work is not included in the above schedule.
Oakleigh Thorne (right), President, MCP, and George Whalen (left) Treasurer, of the Millbrook Community Partnership stand in front of the demolished Kettering Science Center on the campus of former Bennett College. MCP plans to turn it into a 32-acre park.
Bennett College's Carroll Hall after demolition.